Use Benchmarks to build a regional reference cost basis, then compare your estimates with typical construction costs for the same building type and measurement basis. Review the overall cost per area, costs by element, and matched line items to identify where an estimate sits below, within, or above the reference range.
Getting there
- Open the dashboard.
- Select Benchmarks.
- If you have more than one saved basis, choose one from Basis. The list shows the building type, region, number of items, and basis date.
If you do not have an active workspace, select or create one from the switcher in the sidebar before using Benchmarks. A basis belongs to a workspace.
If you have not created a basis yet, select Build a cost basis. If a basis is already displayed, select New basis.
Key concepts
- Region is the market the basis reflects. Enter a market rather than a street address. Use the suggested region spelling where possible.
- Building type is the facility type the basis reflects, such as warehouse, office, retail, multifamily, school, or hospital. You can enter a type that is not in the suggestions.
- Currency sets the currency for the reference rates.
- Area unit sets the unit used for per-area figures. The available displays are sq ft and m².
- Model controls the model used to build the reference cost basis. The available choices are Claude Haiku 4.5, Claude Sonnet 5, and Claude Opus 5.
- A basis contains an all-in cost per area and reference rates grouped by element. Each rate is shown as a low, typical, and high range rather than as a single number.
- The basis date identifies the date reflected by the pricing. The figures are AI-generated reference figures for checking your pricing, not a replacement for a subscription cost service or local quotes.
How to compare Benchmarks
Build or select a basis
- Select Build a reference cost basis or New basis.
- Enter a Region and Building type. Both are required.
- Check Currency and Area unit.
- Choose a Model.
- Select Build basis.
The reference cost basis is saved to your workspace. Building another basis for the same region and building type replaces the existing basis for that combination, so use consistent names for regions and building types.
While the basis is being created, Benchmarks shows Building…. You can select Stop to stop the process. When the basis is ready, it becomes the selected basis.
To compare an estimate, use Compare and select a priced estimate. The list includes the Project name, estimate title, cost per area or total cost, and building type. Select No estimate to return to the basis without an estimate comparison.
Read the comparison
When an estimate is selected, Benchmarks shows:
- The estimate’s cost per area against the reference typical rate, with the low and high ends of the range.
- A result of Within band, Above band, or Below band.
- A comparison by element, including the estimate, reference, range, difference, and impact across the Project’s gross floor area.
- Line items vs reference rates, showing how many line items matched and the net difference against the reference.
- Matched line items sorted by the size of their financial impact. Each matched line shows your rate, the reference typical rate and range, the difference, impact, and result.
A line item is matched only when its unit agrees with a reference item and the CSI code, element, or sufficiently similar description supports the match. Optional line items are not included in the comparison. Unmatched line items are left unscored rather than assigned an unreliable reference.
How to review benchmark elements
- Scroll to Reference unit costs.
- Review the number of priced items and elements shown near the heading.
- Use the element headings to find the part of the building you want to review. Each heading shows its item count and, where available, the typical cost per area.
- Expand or collapse an element by selecting its heading.
- Review each item’s description, confidence, unit, low rate, typical rate, high rate, and basis. The basis explains what the rate includes or excludes.
- Use the range display to see how the typical rate sits between the low and high values.
If an element has no priced items, Benchmarks displays No priced items in this basis yet. Any available caveats appear under What would move these numbers, describing conditions that could materially change the figures.
Tips & things to know
- Choose a basis with the same Area unit as the estimate when you want a per-area comparison. An estimate with no gross floor area cannot be compared per unit area.
- Generate a basis for the Project’s own region and building type where possible. This gives line-item matching the strongest context.
- Keep region and building type names consistent. Two different spellings can create separate saved bases.
- A basis is replaced when you build another one for the same region and building type. Save or note any figures you need before replacing it.
- If no line items match, check the building type, units, element classification, and CSI codes. Benchmarks only scores comparable units and sufficiently related scope.
- A comparison is a review aid. Confirm important rates against local quotes, project-specific scope, specification, labour conditions, and market changes.
- Only workspace owners and admins can delete a saved basis. Select the delete control beside the selected basis, then confirm the action in your browser if prompted.
Warning: Reference figures are AI-generated and exclude GST. Use the stated currency, area unit, basis date, and caveats when deciding whether a result is useful for your Project.
FAQ
Why can’t I compare my estimate per area?
The estimate may not include a gross floor area, or it may use a different area unit from the selected basis. Add the Project size and choose or build a basis using the same Area unit.
Why is my estimate missing from Compare?
Only estimates with a calculated total appear in the comparison list. Check that the estimate has been priced and has a total before returning to Benchmarks.
Why are some line items unmatched?
A line item is scored only when its unit matches a reference item and the CSI code, element, or description provides a reliable match. Unmatched lines remain unscored. A basis for the Project’s own building type can improve matching.
What do Within band, Above band, and Below band mean?
Within band means the estimate rate is between the reference low and high values. Above band means it is higher than the reference high value. Below band means it is lower than the reference low value.
What does the typical rate mean?
Typical is the rate Benchmarks carries when there is no other information. It is the middle point used to show the reference comparison and calculate the difference and impact.
Can I keep multiple bases for the same region and building type?
No. Building a basis for a region and building type that already exists replaces that saved basis. You can keep bases for different regions or building types.
Can I delete a saved basis?
Yes, if you are an owner or admin in the workspace. Select the delete control for the selected basis. Deleting a basis removes it from the workspace and does not delete your Project or estimate.
What if the basis has no priced items?
Review the selected region, building type, Currency, and Area unit, then build the basis again. If the problem continues, use the caveats shown in Benchmarks and validate the needed rates with local pricing information.